Summer 2020
Hinkley Connection Project
Project update National Grid | Summer 2020
Welcome to the summer update Over the last three months we’ve achieved a number of significant milestones to connect low carbon energy. We’ve started work to build the world’s first operational T-pylons, completed two work stages of the 14 that make up the project, and taken down the first of 67km of pylons owned by WPD.
Work starts along the route of the new T-pylon It’s nearly nine years since the innovative T-pylon design scooped first prize in a competition to find the next generation of electricity pylons. Danish engineering firm Bystrup beat 250 rivals to win contest organised by the Royal Institute of British Architects. In May, work finally started in Somerset to build the first operational T-pylons in the world. Our first activity is building a temporary haul road and the road access along the route of the pylons. Once built, the haul road will reduce the amount of construction and other project traffic on local roads
When we are working on public highways we will need to put up traffic lights or close narrow roads to keep everyone safe. We’ve already completed work to build a road access south off the A38 near Rooks Bridge and on Causeway in Woolavington
The table below show where we are currently carrying out work and all the locations where we will build haul road access and crossing point along the route. We recognise this work will cause delays to journeys and we’re sorry for any inconvenience. We’re working closely with our contractor, Balfour Beatty, to reduce disruption as best we can and aim to complete the roadworks as quickly as possible. Before work starts, we will write to nearby residents and keep parish councils updated. More information, including detailed information on locations and timings for our roadworks, can be found on our project website www.hinkleyconnection.co.uk/in your area or by calling our community relations team on 0800 377 7347.
Location Parish Scheduled dates More information
Pill Road Rooks Bridge 13 July to 15 October Road closure
Butt Lake Road Mark Causeway 13 July to 9 August Road closure
Burtle Road East Huntspill 10 August to 11 September Road closure
Factory Lane East Huntspill August TBC Traffic lights
B3141 The Causeway Woolavington 1 to 30 September Traffic lights
A39 Puriton Hill Puriton 1 to 30 September Traffic lights
Country lane south
of Southwick Farm Southwick 1 to 30 September Road closure
Vole Road Mark 1 October (TBC) to 1 November Road closure
A39 Bath Road Bridgwater 1 October to 1 November Traffic lights
Southwick Road Southwick 1 October to 1 November Road closure
Woolavington Road Woolavington October 2020 to November 2020 Traffic lights
Northwick Road Mark November to December 2020 (TBC) Road closure
B3141 The Causeway Woolavington December 2020 to January 2021 (TBC) Traffic lights
Please note these dates may change at short notice.
We recognise this work will cause delays to journeys and we’re sorry for any inconvenience. We’re working closely with our contractor, Balfour Beatty, to reduce disruption as best we can and aim to complete the roadworks as quickly as possible. Before work starts, we will write to nearby residents and keep parish councils updated. More information, including detailed information on locations and timings for our roadworks, can be found on our project website www.hinkleyconnection.co.uk/in your area or by calling our community relations team on 0800 377 7347.
Posted 15th August 2020