PROGRESS REPORTS

Please note that daily progress reports are subject to change – please regularly check email updates before travelling or sign up for instant text alerts.

Weekly update number 13

dated 1st July 2016

 

We have made good progress on this scheme over the last few months and have managed to gain some significant time over the duration of the work which has brought our finishing date forward.

 

We are now in a position where we are confident that we will be finished on the road section with the road re-opened by 8 July next week.

 

Next week we will be reinstating the road where we have just completed the last section of work, reinstating verges (where required) and CCTV’ing the new sewer for our records.  

 

Thank you all very much for your cooperation during this time.

 

Kind Regards

 

Andy

 

Andy Roberts

Project Manager - Networks

Wessex Engineering & Construction Services

Telephone : 0345 600 4 600

DEF

 

Weekly update number 12 

dated 27th June 2016

 

 

Last Week

 

We completed construction of the manhole outside MH7a (Ryedown)

 

This Week

 

Reinstatement of the road up to MH7a was completed today

Excavate down on existing vacuum sewer main and expose pipework

Excavate a trench across the road for new pipework and connect pipework. Back fill excavation and reinstate the road

 

I will send out a further update on Friday with details of the proposed work for the following week.

Kind Regards

Andy 

 

Andy Roberts

Project Manager - Networks

Wessex Engineering & Construction Services

Telephone : 0345 600 4 600

DEF

 

 

Weekly update number 11 

dated 17th June 2016

 

This Week

 

Manhole 7 has been completed and we have backfilled and reinstated from this manhole  up to Croft Farm.  The trench up to 5m before the manhole at Ryedown has been excavated and the pipe will be laid up to this point today.  Backfilling of the trench will commence today and the road will be reinstated on Tuesday next week.

 

Next Week

 

The remaining 5m of trench will be excavated up to Ryedown. Excavation and construction of the manhole outside Ryedown (manhole 7a) will be undertaken and we will start on the trench line up to Manhole 8 (boundary of Ashview and Meadow Gate)

 

 

 

Weekly update number 10 

dated 9th June 2016

 

This Week

 

We have completed the excavation works for manhole 7 (Stone Gables) and will have installed the manhole base and connected up all pipework by the end of tomorrow. 

 

We have also started excavating towards manhole 8 ( located at Ryedown) and have excavated  approximately 25% of the road up to Croft Farm.

 

Next Week

 

Manhole 7 will be completed and backfilled. The trench up to Croft Farm will be backfilled and tarmac reinstated. Excavation for the new pipework will continue towards Ryedown.

 

 

 

Weekly update number 8 

dated 27th May 2016

 

 

 

This Week

 

Manhole 6 (outside Pippins) has now been completed and backfilled. Tarmac reinstatement will be completed today. Excavation has started in the road heading towards Manhole 7 (Stone Gables).

 

Next Week

 

Excavation for the new pipe will continue along the road away from Manhole 6 with the aim of reaching Manhole 7 by  the end of next week.

 

Kind Regards

Andy 

 

Andy Roberts

Project Manager - Networks

Wessex Engineering & Construction Services

Telephone : 0345 600 4 600  

DEF

 

 

 

 

 

 

Weekly update number 7 below

dated 20th May 2016

 

This Week

 

We have excavated and laid the pipework up to manhole 6 (outside the hairdressers). The road up to this point has been reinstated and the excavation required to construct manhole 6 has been completed.

 

Next Week

 

Manhole 6 will be constructed and pipework will be laid away from manhole 6 towards manhole 7 (situated outside Stone Gables)

 

Kind Regards

Andy 

 

Andy Roberts

Project Manager

Wessex Engineering and Construction Services

Wessex Water

0345 600 4 600

 

 

 

 

Weekly update number 6 below

dated 13th May 2016

 

This Week

 

Manhole 5 (situated outside Whites Farm/ Pirran) has now been completed and the road has been reinstated up to it. Laying of the new pipework between manhole 5 and manhole 6 has continued this week.

 

Next Week

 

We should complete all pipework between manhole 5 and manhole 6 (outside hairdressers) ready to begin the construction of manhole 6.

 

Kind Regards

Andy 

 

 

Andy Roberts

Project Manager

Wessex Engineering and Construction Services

Wessex Water

0345 600 4 600

Weekly update number 5 below

dated 6th May 2016

 

This Week

 

The base slab for manhole 5 (situated outside Whites Farm/ Pirran) has now been poured and the first manhole ring has been placed. The road has been excavated away from manhole 5 and pipework has been laid towards manhole 6 (outside hairdressers)

 

Next Week

 

We will complete the construction of manhole 5 and backfill the pipeline which runs to and from it. The pipeline between manhole 5 will also continue to be laid towards manhole 6.

 

Kind Regards

Andy 

 

 

Andy Roberts

Project Manager

Wessex Engineering and Construction Services

Wessex Water

0345 600 4 600

 

 

 

Weekly update number 4 below

dated 29th April 2016

 

This Week

 

We have excavated and laid pipework up to manhole 5 (situated outside Whites Farm/ Pirran). The concrete surrounding this manhole has been broken up and removed in preparation for the new replacement manhole. We have also reinstated the road around manhole 4 and up to manhole 5.

 

Next Week

 

Starting from Tuesday the base slab will be poured for manhole 5 and construction will continue on this manhole while we begin to lay new pipework towards manhole 6 (outside hairdressers)

 

Kind Regards

Andy 

 

 

Andy Roberts

Project Manager

Wessex Engineering and Construction Services

Wessex Water

0345 600 4 600

 

 

Posted on website - 2nd May 2016

 

 

 

 

 

 

 

As our construction will now be to the east (Mark C of E School end) of Mark Causeway from now until the end of the scheme, I will no longer be issuing out a drawing indicating the direction of entry for Poplar Lane, as it will be from the west (M5 motorway end) until the end of February.

 

In addition, as our work on Mark Causeway  will be fairly similar week to week, I will now issue an email once a month to inform you of our work, unless there are any delays to our completion date. Our site team will liaise directly with residents affected by our work to discuss any alternative arrangements to property access.

 

We are still finalising arrangements with the landowner affected by our recent change in design for the Poplar Lane sewer diversion and cannot at this time provide firm dates for the Poplar Lane works, however we will be in contact with these residents once discussions have been completed.

 

Progress for January, 2016

 

Construction of manholes and sewer will continue along Mark Causeway to the east of Poplar Lane (note all works to the west of Poplar Lane (M5 motorway end) have now been completed).

 

We are still on track for completion of work on Mark Causeway by 29 February 2016.

 

Thank you for your ongoing patience and co operation during our essential flood alleviation work. If you have any further queries, please contact me on 0345 600 4 600 (Mon to Fri, 8am to 6pm) or on this email address.

Regards,
 
Joo Foo  

 

 

Posted on website - 29th January 2016

 

 

 

 

 

 

 

 

 

 

There will be no work on Mark Causeway from 25 December to 3 January, and Mark Causeway will fully open to traffic during this time, with temporary traffic signs removed.

 

Anticipated Progress for week commencing 4 January, 2016

 

On 4 January, the Mark Causeway Road Closure will be reinstated, including the temporary traffic signs.

 

Access to Poplar Lane will now swap to the west (M5 motorway end) of Mark Causeway as installation of the new gravity sewer and manholes continues eastwards along Mark Causeway.

 

Please access Poplar Lane from the west (M5 Motorway end) of Mark Causeway (please see attached drawing wc 4 Jan)

 

Thank you for your ongoing patience and co operation during our essential flood alleviation work. If you have any further queries, please contact me on 0345 600 4 600 (Mon to Fri, 8am to 6pm) or on this email address.

 

Wishing you all a Merry Christmas and Happy New Year.

Regards,
 
Joo Foo  

 

 

 

Added to website on 29th December 2015

 

 

 

 

 

Anticipated Progress for week commencing 21 December, 2015

Construction of manholes and sewer on the west side of Poplar Lane will be completed this week. Mark Causeway will be fully reinstated and signage and fencing removed on 24 December to allow traffic during Christmas / New Year period. Mark Causeway road closure will be back in place on 4 January.

 

Please access Poplar Lane from the east (Mark C of E School end) of Mark Causeway (please see attached drawing wc 21 Dec)

 

Thank you for your ongoing patience and co operation during our essential flood alleviation work. If you have any further queries, please contact me on 0345 600 4 600 (Mon to Fri, 8am to 6pm) or on this email address.

Regards,
 
Joo Foo
Project Manager
Networks
E. joo.foo@wessexwater.co.uk

Added to website on 17th December 2015

 

 

 

 

 

Poplar Lane Access wc 16 Nov.pdf
Adobe Acrobat document [93.4 KB]

Anticipated Progress for week commencing 16 November, 2015

 

Construction of manholes and sewer will continue on the west side of Poplar Lane. Piling will continue and is expected to be completed this week. Although piling will be on both sides of Poplar Lane, access past the piling rig on the east will be possible.

 

Due to further review of our design for the Poplar Lane sewer, the road closure in Poplar Lane will now be delayed until 23 November. Further information will be given to the residents of Poplar Lane next week.

 

Please access Poplar Lane from the east (Mark C of E School end) of Mark Causeway (please see attached drawing wc 16 Nov)

 

Thank you for your ongoing patience and co operation during our essential flood alleviation work. If you have any further queries, please contact me on 0345 600 4 600 (Mon to Fri, 8am to 6pm) or on this email address.

Regards,
 
Joo Foo
Project Manager
Networks
E. joo.foo@wessexwater.co.uk

Poplar Lane Access wc 9 Nov.pdf
Adobe Acrobat document [93.4 KB]

 

6th November 2015

 

 

 

As the area of closed road will be on the west (M5 motorway) side of Poplar Lane for the rest of this and next week, I will be issuing a weekly progress report for week commencing 9 November rather than a daily progress report. I will notify you the day before should this situation change.

 

Anticipated Progress for week commencing 9 November, 2015

Construction of manholes and sewer will continue on the west side of Poplar Lane. Piling will commence and is expected to be completed within the week. Although piling will be on both sides of Poplar Lane, access past the piling rig will be possible.

 

Please access Poplar Lane from the east (Mark C of E School end) of Mark Causeway (please see attached drawing wc 9 Nov)

 

Thank you for your ongoing patience and co operation during our essential flood alleviation work. If you have any further queries, please contact me on 0345 600 4 600 (Mon to Fri, 8am to 6pm) or on this email address.

Regards,
 
Joo Foo
Project Manager
Networks
E. joo.foo@wessexwater.co.uk

 

 

 

3rd November 2015

 

Progress for 4 November, 2015

Work on the new manhole and pipework has continued to the west of Poplar Lane.  

Please access Poplar Lane from the east (Mark C of E School end) of Mark Causeway (please see attached drawing 4 Nov – no change).

 

Anticipated Progress for 5 November 2015

Work on new manhole and pipework will continue to the west of Poplar Lane. Additional trial holes will be undertaken to the east of Poplar Lane to prove the location of existing services along the proposed sewer route, however resident access vehicle traffic will be able to pass these works.

Please access Poplar Lane from the east (Mark C of E School end) of Mark Causeway (please see attached drawing 5 Nov)

 

30th October 2015

 

 

Dear All,

 

We would like to start sending out progress reports to inform residents on where we will be working so that you will be able to better plan your journeys around our road closure, and also for those that are interested in the flood alleviation scheme we are constructing. Please feel free to forward this onto other people, or ask them to send me their email address to be included in this circulation. We can also offer an instant report summary via text message if you forward through your mobile phone number. If you do not wish to receive this email, please let me know and I will remove you from the list.

 

The reports will be issued daily until we start on the main sewer run to the east of Poplar Lane, as we will need to inform Poplar Lane residents on which side to access. Unfortunately due to the nature of the work, we are unable to provide more of a lookahead. However, once the construction to the east of Poplar Lane commences, the progress reports will be on a weekly basis as all access to Poplar Lane will be to the west during this time.

 

Progress for 30 October 2015

Wessex Water are completing trial holes to the east of Poplar Lane, which will verify existing services in the area of the new manhole to be piled. Please access Poplar Lane from the west (motorway end) of Mark Causeway (please see attached drawing 30 Oct)

 

Anticipated Progress for 2 November 2015

Piling will commence to the west of Poplar Lane. Please access Poplar Lane from the east (Mark C of E School end) of Mark Causeway (please see attached drawing 2 Nov)

 

Thank you for your ongoing patience and co operation during our essential flood alleviation work. If you have any further queries, please contact me on 0345 600 4 600 (Mon to Fri, 8am to 6pm) or on this email address.

Regards,
 
Joo Foo
Project Manager